Birch Bay Lynden Road Paving – Enterprise Rd. to Rathbone Rd.

Summary

This project will repave about two miles of Birch Bay Lynden Road between Enterprise and Rathbone roads, and add rumble strips and new pavement markings. There will be single-lane closures and significant travel delays.

  • This project is expected to start Aug. 2 and continue for about a month.
  • Drivers should expect single-lane closures and significant delays.
  • Please avoid the area if possible.

Preliminary paving schedule: 

  • Week 1 Aug. 2-6: Clear vegetation, remove curb, asphalt planning, and crack seal.
  • Week 2 Aug. 9-13: Road and driveway apron paving
  • Week 3 Aug. 16-20: Grading, shoulder work, raise guardrail.
  • Week 4 Aug. 23-23: Add rumble strips, striping.

Contact Us

  1. Cody Swan

    Project Engineer
    (360) 815-3803
    cswan@co.whatcom.wa.us
     
    322 N. Commercial Street, Suite 301
    Bellingham, WA 98225


    Phone: 360-778-6210
    Fax: 360-778-6211


Project Overview:

  • Status: Contract awarded.
  • Next Steps: Construction.
  • Schedule: This project is expected to start Aug. 2 and continue for about a month.
  • Construction Contractor: Granite Construction 
  • Contract Amount: $909,770.00