Truck Road Fish Passage Project

Truck Rd Detour Map 2021

Contact Us

  1. Ben Floyd, P.E.

    Project Engineer 

    360-778-6252 

    bfloyd@co.whatcom.wa.us

Project Overview:

  • Status:  Construction
  • Schedule: July 12 - September 2021
  • Funding: Paid for with local funds, not grants. 
  • Work performed by County Maintenance and Operations Division.


This project was completed on Sept. 23, 2021.

Summary

This project will replace a 60" concrete fish barrier culvert with a 16'10" aluminum box culvert to meet fish passage standards. 

  • Removes a fish barrier culvert.
  • Improves fish habitat.

Traffic Impacts

Truck Road will be closed at the project location starting July 12 with construction expected to last into early fall. 

Project Updates

This page will be updated regularly during construction.


Photos of a similar aluminum box culvert installed on Northwest Drive in 2020

Example of a box culvert 2
Example of a box culvert 1